April 8 Construction Update

  • 20170408_041611
  • 20170408_041722
  • 20170408_071155
  • 20170408_071217
  • 20170408_101524
  • 20170408_102304
  • 20170408_105457
  • 20170408_130033

Sully-Miller will do:

  • LCB_RS placement.
  • Roadway subgrade and base compaction.

IMPORTANT NOTE: Please pay close attention for deviations in delineation of the traffic control. Obey flagmen as noted in the above-stated area as it will change on a daily basis during the week. Speed limits will remain lowered at 30 mph and is strictly enforced. Tickets are doubled in construction zones. A detour to Sheila on the south is highly suggested from Fidelia Ave to Eastern Ave. This work is only tentative and can change on a very short notice the day of the work.

Disclaimer: All work is tentative and should be verified prior to use.

For questions, information and updates:
Visit project website: www.washingtonblvdcommerce.com
E-mail: info@washingtonblvdcommerce.com
Call Project Hot Line: (888) 705-4009 (toll free)

Comments are closed.